Phase C (Plant 3)
September 2019
-
Storm Pond Bentonite Treatment
-
Disinfection Building
-
Disinfection Building Foundation
-
Disinfection Building Foundation
-
Contact Chamber Wall Forms
-
Contact Chamber Wall Forming
-
Disinfection Building Wall Forming
-
Disinfection Building Wall Forms
October 2019
-
Disinfection Building Walls
-
Dewatering Building Excavation
-
Contact Chamber Wall Forms
-
Disinfection Building Walls
-
Storm Pond Concrete Base Slab
-
Contact Chamber Wall Forms
-
Storm Pond Drain Line Install
-
Storm Pond Drain Line Install
-
Storm Pond Drain Line Install
-
Dewatering Building Excavation
-
Storm Pond Concrete Base Slab
-
Storm Pond Drain Line Install
-
Dewatering Building Excavation
-
Storm Pond Concrete Base Slab
-
Dewatering Building Foundation
-
Dewatering Building Foundation
-
Storm Pond Concrete Base Slab
-
Storm Pond Concrete Base Slab
-
Storm Pond Drain Line
-
Storm Pond Inlet Structure
-
Storm Pond Concrete Base Slab
-
Dewatering Building Wall Forms
November 2019
-
Dewatering Building Walls
-
Dewatering Building Pipe Sleeves in Walls
-
Headworks Building Excavation
-
Contact Chamber Base Slab
-
Contact Chamber Base Slab
-
Disinfection Building Wall Forms
-
Contact Chamber Wall Forms
-
Storm Pond Base Slabs
-
Contact Chamber Wall Pour
-
Head Works Building Base Slab
-
Contact Chamber Wall Forms
-
Contact Chamber Walls
-
Head Works Building Base Slab
-
Pump Station Building Excavation
-
Contact Chamber Walls
-
Head Works Building Base Slab
-
Dewatering Building Suspended Floor Forms
-
Storm Pond Rip Rap Sides
December 2019
-
Headworks Building Wall Forms
-
Pump Station Base Slab
-
Dewatering Building Suspended Floor Pour
-
Contact Chamber Walls
-
Disinfection Building
-
Contact Chamber Walls
-
Disinfection Building
-
Pump Station Wall Forms
-
Contact Chamber Center Section Demolition
-
Contact Chamber Center Section Demolition
-
Headworks Wall Framing
-
Headworks Wall Framing
-
Grit and Pump Station Wall Framing
-
Grit and Pump Station Walls
-
Headworks Wet Well Wall Framing
-
Headworks Iron Work for Bar Screen Channels
-
Grit and Pup Station Walls
-
Filtrate Holding Basin Wall Forms
-
Filtrate Holding Basin Walls
-
Disinfection Building Floating Floor Poured
-
Demolition on Center Section of Contact Chamber
-
Grit and Pump Station Wall Lift
-
Wall Forms for Headworks Building
-
Grit and Pump Station Wall Lifts
-
Filtrate Holding Basin Wall Poured
-
Iron Work for Bar Screen Channels in the Headworks Building
-
Wall Masonry on Dewatering Building
January 2020
-
Pump Station Piping and Vault Install
-
Pump Station Piping and Vault Install
-
Contact Chamber Middle Section Demolition
-
Contact Chamber Middle Wall Rehab Framing
-
Contact Chamber and Disinfection Building
-
Headworks Building Channel Framing
-
Disinfection Buiding Masonry
-
Dewatering Building Holding Tank
-
Headworks and Pump Station Lower Level Concrete Work
-
Headworks Building Concrete Work
-
Grit and Pump Station Concrete Work
-
Disinfection Building Roofing
-
Headworks Main Inlet Pipe Installation
-
Dewatering Building Roof Installation
-
Contact Chamber Wall Concrete Pumping
February 2020
-
Main Plant Inlet Line Installation
-
Contact Chamber Middle Section Rebuild
-
Tank Drains Structure
-
Parts for Main Headworks Building
March 2020
-
Mechanical piping dewatering building basement
-
Mechanical piping dewatering building basement
-
Contact chamber center section wall forms almost complete and ready for concrete
-
Tank drainage structure
-
Mechanical piping outside disinfection building
-
Main control room pads formed in dewatering building
-
Headworks grit station foundation
-
Mechanical piping feeding dewatering building
-
New pumps arrive for the dewatering building basement
-
Disinfection building storage garage
-
Disinfection building basement plumbing
-
New electric feed line to disinfection building
-
Completed wall raises on contact chamber
April 2020
-
Headworks Building Masonry
-
Disinfection Building Roof Installation
-
Completed Contact Chamber
-
04 - Disinfection Building Siding Installation
-
Dewatering Building Electrical Installation
-
Headworks Masonry
-
Headworks, Grit Building, Pump Station Masonry
-
Diversion Box Gate Installation
-
Clarifier Piping Replacement Excavation
-
Headworks Bar Screen Gate Installation
-
Headworks Bar Screening Conveyor
-
Grit Building Masonry
May 2020
-
Pump Station and Grit Building Masonry
-
Headworks Roof Trusses
-
Headworks Roof Trusses
-
Grit Conveyor Hoisted into the Grit Pump Station Before the Roof was Constructed
-
Mechanical Piping and Pumps Installation in Dewatering Building Basement
-
Mechanical Piping and Pumps Installation in Dewatering Building Basement
-
Mechanical Piping and Pumps Installation in Dewatering Building Basement
-
Mechanical Piping and Pumps Installed in Dewatering Building Basement
-
Mechanical Piping and Pumps Painted in Dewatering Building Basement
-
Mechanical Piping and Pumps Installation in Dewatering Building Basement
June 2020
-
Mechanical Piping and Pumps Painted in Dewatering Building Basement
-
Ramp Installation into Storm Pond
-
Storm Pond Rip Rap and Ramp Installation
-
Disinfection Storage Tanks Installed
-
Disinfection Storage Tanks Installed
-
Non-Potable Water Piping and Pump Installation
-
Grit Conveyor Pump Station Building
-
Grit Classifier Installation
-
Electrical Panel Installation at Headworks Building
-
Screening Conveyor Installation at Headworks Building
-
Screening Compactor Installed in Headworks Building
-
Coring New Piping into East Package Plant
-
Grit Separator Ready for Inspection
-
Dewatering Building Spiral Screw Press Installation
-
Screw Press Dewatering Holding Tank
-
Screw Press Conveyor Ready for Installation
-
Influent Pump Station
-
Influent Pump Station
July 2020
-
Generator Pad
-
Non-Potable System
-
Non-Potable System
-
Grit Pump Station Piping
-
Pylons for Slidge Storage Canopy
-
Grit Pump Station Piping
-
Generator Pad
-
East Package Plant Renovation
-
Blower Building Renovation
-
Sludge Storage Canopy Graded for Base Slab
-
New Concrete Drive by Disinfection Building
-
Sludge Storage Canopy Beams Painted
-
East Package Plant Renovation
-
Sludge Storage Canopy Base Slab
-
Grit Station Piping
-
Grit Station Seperator
-
East Package Plant Renovation
-
Blower Building Renovation
-
Blower Building Renovation
August 2020
-
Generator Being Set in Place
-
Influent Pump Station Pumps Ready for Installation
-
East Package Plant Renovation
-
Sludge Storage Canopy Base Slab
-
Screw Press Conveyor Installed
-
Non-Potable System